Handover actions
4 commissioning or test records note items still to do. Each certificate is in the manual exactly as it came in.
Demo: on a live job the PM decides here.
TPS commissioning sheet, P B.04 LTHW to DHWS primary pumps.pdf
Close-out requested
TPS Ltd · Asset P B.04 · Raised 6th of May 2026 · 2 requests sent, last on 3rd of June 2026
HEN0203-PB04-CC
1 open item, in the record's words
We've asked TPS Ltd for the fix and an updated certificate (2 requests so far), and we keep asking until it's closed. The certificate is in the manual as received, so the O&M isn't held up.
Ashton fire damper testing report, 18th of March 2026.pdf
Close-out requested
RJ Ashton Group (Ashton Fire Specialists) · Asset FD 0.01 · Raised 8th of May 2026 · 2 requests sent, last on 29th of May 2026
HEN0203-FD001-FD
6 open items, in the record's words
FD/04 Changing Rooms: drop tested No, fire stopped No
Page 11 of the recordSee it in the manual, Vol 8, p 40FD/10 Main Gym: No Access. Solid ceiling, ceiling hatch required. Estates to address
Page 24 of the recordSee it in the manual, Vol 8, p 53FD/13 Plantroom: remedial, 400x400 on each side
Page 31 of the recordSee it in the manual, Vol 8, p 60FD/14 Plantroom: remedial, 400x400 on side
Page 33 of the recordSee it in the manual, Vol 8, p 62FD/16 Plantroom: panel needs fitting on other side of duct
Page 37 of the recordSee it in the manual, Vol 8, p 66FD/17 Plantroom: door needs fitting on other side
Page 39 of the recordSee it in the manual, Vol 8, p 68
We've asked RJ Ashton Group (Ashton Fire Specialists) for the fix and an updated certificate (2 requests so far), and we keep asking until it's closed. The certificate is in the manual as received, so the O&M isn't held up.
Ashton ventilation ductwork cleaning report, 17th of March 2026.pdf
Close-out requested
Linden Ductwork · Asset Ventilation · Raised 8th of May 2026 · 1 request sent, last on 22nd of May 2026
HEN0203-VENT-OT
1 open item, in the record's words
We've asked Linden Ductwork for the fix and an updated certificate (1 request so far), and we keep asking until it's closed. The certificate is in the manual as received, so the O&M isn't held up.
Ashton DHWS balancing and outlet temperature record.pdf
Close-out requested
RJ Ashton Group (Ashton LLP) · Asset Domestic water · Raised 15th of May 2026 · 3 requests sent, last on 9th of June 2026
HEN0203-DWS-WH4
2 open items, in the record's words
We've asked RJ Ashton Group (Ashton LLP) for the fix and an updated certificate (3 requests so far), and we keep asking until it's closed. The certificate is in the manual as received, so the O&M isn't held up.
KVT BMS commissioning checklist, 14th of May 2026.pdf
Accepted as open at handover
KVT Controls · Asset BMS · Raised 15th of May 2026 · 2 requests sent, last on 28th of May 2026
ELS-CC-05
4 open items, in the record's words
Main pool PHX valve control: unable to test fully as no pool water
Page 2 of the recordSee it in the manual, Vol 9, p 132Main and learner pool water meters: unable to calibrate as no usage
Page 2 of the recordSee it in the manual, Vol 9, p 132Pool plant common alarm and pool booster enables: pool plant not yet commissioned
Page 2 of the recordSee it in the manual, Vol 9, p 132VRF BlackPear BACnet config, pull points, graphic maps and wall controller test vs BMS not checked
Page 2 of the recordSee it in the manual, Vol 9, p 132
Listed in the manual's open items table (Appendix A) so your client knows. We've stopped asking.
Accepted as open at handover by Project manager on 2nd of June 2026. Reason: Example PM note for this demo: pool plant is commissioned once the pools are filled, after handover. Client told at handover.
Trane commissioning visit report 12th of May 2026, ASHP 0.01 and 0.02.pdf
Resolved
Trane UK Ltd · Asset ASHP 0.01 to 0.03 · Raised 13th of May 2026 · 1 request sent, last on 20th of May 2026
ELS-CC-06
3 open items, in the record's words
Not listed in the manual. We've stopped asking.
Marked as resolved by Project manager on 2nd of June 2026. Note: Example PM note for this demo: Trane returned in May; the ASHP 0.03 start-up report (27th of May) is in the manual.